Skip to main content
Question

how do i make a pm quarterly

  • February 19, 2026
  • 1 reply
  • 126 views

I'm new on here and setting up some preventative maintenance and haven't been able to do quarterly inspections or work. Just wondering if there's something i'm missing. 

1 reply

AngelinaE
Forum|alt.badge.img
  • MaintainX Team
  • February 23, 2026

Hi Ron, thanks for asking! 

You’re going to use the Recurrence function to set your new PMs to Quarterly:

  1. In your work order, scroll down to the Schedule settings.

     

  2.  You’ll change Schedule to ‘Calendar’, and Work Type to ‘Preventive’.
    This opens the ‘Recurrence’ settings.

     

  3. You’ll set Recurrence to ‘Monthly by date’.

     
  4. Change it to every 3 months, and select the applicable date.

     

 

When you save your PM, it’s now set to recur on a quarterly basis. 

Let me know if you have any follow-up questions!