In the event someone forgets to put an asset back online is there a means to go back later and adjust the asset downtime? I have looked at the work order and the asset and just don’t see a way to do this. My downtime report is inaccurate, and I need to figure out how to correct it.

Best answer by James Beers

If you go to the asset, it will show the status. Click on the “see more” to the right. It will give you the graph of the downtime. You can click on the latest input and adjust the time and date there. Click on the 3 dots on the status information. It will allow you to “edit status” from there.

1 reply

James Beers
Forum|alt.badge.img+5
  • Advanced Operator
  • Answer
  • May 30, 2025

If you go to the asset, it will show the status. Click on the “see more” to the right. It will give you the graph of the downtime. You can click on the latest input and adjust the time and date there. Click on the 3 dots on the status information. It will allow you to “edit status” from there.